Projects

  • Bathurst Aquatic Centre,
  • NSW
  • This project was procured from a design competition headed by Buildcorp and Peter Hunt Architects. This new community facility offers the burgeoning public of Bathurst a new aquatic centre comprising a heated outdoor 50m pool, indoor heated 25m pool, program pool, leisure/ toddlers pool, spa, sauna, steam room and amenities.
    Use of this facility is available all year round in an otherwise cool climate, via an environmentally sustainable co-generational heating system.
  • Client
  • Bathurst Regional Council
  • Project Manager
  • Architect
  • Peter Hunt Architects
  • Contract sum
  • $11,700,000.00
  • Project size
  • 12000m²
  • Program
  • 72 weeks
  • Completion
  • Sep 2007